WLLR’s No.822 – February 2020

WLLR’s No.822 – February 2020

WLLR’s ‘Earl’ has seen alot of action over the last month. The axleboxes have been prepared with new white metal being cast. The horn guides have been prepared and drilled ready for assembly and machining. The water tank filler lids have seen attantion as has the roof...
Garratt No.60 – February 2020

Garratt No.60 – February 2020

No.60 has seen much work over the last month. A full inspection of the chassis and components. The wheelsets for the front power unit have been profiled, repainted and reinstalled. New brake blocks have been fitted during the reassembly process. The new piping for the...
Caravan & Camping Show 2020

Caravan & Camping Show 2020

The Caravan & Camping Show 2020 took place at the NEC Arena, Birmingham, between the 18th & 23rd February.  We attended the show as part of a coalition titled ‘Rails in Mid Wales’, working with Cambrian Rail Partnership and Talyllyn Railway to...