Carriage No.11 – September 2019

Carriage No.11 – September 2019

Carriage 11 has been progressing closer towards entry to service with the interior wall panel being lacquered, the intricate detail work being built up within the carriage interior and a storage area being custom built for storage of the guard’s equipment, including a...
Baldwin No.44699 – September 2019

Baldwin No.44699 – September 2019

The Baldwin is starting to look like it a 10-12-D, but much is still to be done. The engine has had new cab side and front sheets fabricated for it and the original roof and ironwork has been removed from the old cab and temporarily bolted to the new parts, pending...
Station Project Update

Station Project Update

The station project has been a little quiet since the completion of our new platform, whilst drawings and contracts for the next stage of the project have been getting agreed.  One job that has been completing is the rebuilding of the boundary wall and fence, a...
Garratt No.60 – September 2019

Garratt No.60 – September 2019

Work has been progressing on the Garratt as its entry to service grows closer. The fabrication of the spark arrestor assembly has been completed, and lapping of the joints, to ensure a good seal, has been taking place on the large steam pipes that run beneath the...